Quang Binh: Ensuring the handover progress of the North – South expressway project

(Construction) – The East North-South Expressway construction project in the 2021-2025 period, the section through Quang Binh province with a total length of 126km, is being focused on site clearance according to the schedule.

Mr. Tran Thang – Chairman of the People’s Committee of Quang Binh province inspects the site clearance and intersection in Le Thuy district.

Up to now, the field inventory of the project in Le Thuy, Quang Ninh, Bo Trach, Quang Trach districts, Ba Don town and Dong Hoi city has been basically completed, with a rate of 90-100%. . Quang Trach district and Dong Hoi city have issued decisions approving compensation, support and resettlement plans. The remaining districts and towns are applying prices, making compensation and support plans for the first phase.

The Provincial Traffic Construction Investment Project Management Board is coordinating with the People’s Committees of districts: Le Thuy, Quang Ninh, Bo Trach, Ba Don town to approve the task of making detailed planning at scale 1. /500 resettlement sites.

According to the plan, by November 20, 2022, Quang Binh will hand over 70% of the project site through the province. 6 districts, towns and cities continue to coordinate with the Department of Transport and the Project Management Boards (under the Ministry of Transport) to review the alignment, design agreement on crossings, overpasses, and collection roads. , underground tunnels, sewers, return irrigation works… to submit to the Provincial People’s Committee for comments with the Ministry of Transport.

It is expected that the project site will be held in Phu Thuy commune (Le Thuy district) in the Van Ninh – Cam Lo segment (km0 – km68). Currently, the consulting unit is urgently preparing the technical design and cost estimate for verification, appraisal and approval as a basis for selecting construction contractors to start the project.

Mr. Tran Anh Tuan – Deputy Director of the Department of Transport of Quang Binh province said that the preparation of site clearance for the project with a total land area approved by the Ministry of Transport is 880ha. The number of households to be resettled is 864 households; the estimated number of resettlement areas is 38 areas with an area of ​​about 86.43 ha; 2,863 graves had to be relocated and 17 positions were arranged with an area of ​​126.29ha.

The investors have made 125.85km ground clearance piles, reaching 100%. Currently, the localities with the project passing through are organizing inventory and tally of the volume of assets, the number of affected households, the number of households having to be resettled. Total cost of compensation, support and resettlement is expected to be more than 4,078 billion VND.

For construction and expansion works within the project scope, the People’s Committees of districts, cities and towns have organized propaganda and mobilized 65/114 households with construction works to voluntarily dismantle them. unloading; Currently, there are 49 households with construction and expansion works on the route, of which: Quang Trach district has 31 households, Quang Ninh district has 2 households and Le Thuy district has 9 households.

Chairman of the People’s Committee of Quang Binh province, Mr. Tran Thang requested that, for the parts that have not yet made progress, localities, units, departments and branches must urgently complete them as soon as possible. Review, synthesize, and promptly report all obstacles in the process of performing tasks such as: Planning 1/500 of resettlement areas, reviewing connection points and intersections of highways with residential roads… Ensure handing over the site to build the project according to the set timelines.

People in Quang Trach district dismantle the offending works to serve the construction of the expressway.

Localities need to implement and complete legal documents in accordance with the provisions of the law, to avoid loss of State property during the process of land acquisition and handing over the site to the construction unit.

It is known that to implement this key project, Quang Binh province has to resettle for 653 households in 6 districts, cities and towns; affecting more than 50 hectares of residential land, more than 160 hectares of agricultural land, nearly 670 hectares of forest land and 61,532 housing projects.

Quang Binh province is mobilizing the whole political system to step in to speed up site clearance and find settlement solutions for affected people.


The article is in Vietnamese

Tags: Quang Binh Ensuring handover progress North South expressway project

PREV How are the dead rhinos in the ecological zone handled?
NEXT Vinamilk is the most valuable food brand in Vietnam and the sixth largest dairy brand in the world