Dak Lak develops detailed plan for Khanh Hoa Expressway Project

Dak Lak province aims to hand over 70% of the site area of ​​the bidding packages to start the Khanh Hoa – Buon Ma Thuot Expressway Project before June 30, 2023.

Dak Lak Provincial People’s Committee has just issued Plan No. 179/KH-UBND dated September 15, 2022 to implement the Resolution of the XV National Assembly and the Government’s Resolution on investment policy of Khanh Hoa Expressway Project – Buon Ma Thuot, phase 1.

According to this plan, Dak Lak province will organize and prepare an environmental impact assessment report for the decentralized component project, completed before November 12, 2022, and send it to the Ministry of Natural Resources and Environment for appraisal and approval. Browser.

At the same time, organize the formulation, verification, appraisal and approval of component projects which are decentralized, completed before January 20, 2023 and carry out the following works to ensure that construction begins before June 30. 2023.

Dak Lak province aims to hand over 70% of the site area of ​​construction and installation bidding packages starting before June 30, 2023 and basically hand over the remaining area before December 31, 2023. Completing some sections of the route with high traffic volume in 2025, basically completing the entire route in 2026 and putting the whole project into operation in 2027.

The Provincial People’s Committee assigns the project investor who is the Investment Project Management Board to construct traffic works and agriculture and rural development The province to develop detailed implementation plans to ensure the completion of milestones as required. requirements of the Resolutions of the National Assembly and the Government.

Carrying out selection of design consultancy contractors, supervision consultants… simultaneously implementing work related to compensation, site clearance, support, resettlement, preparation, submission for appraisal, project approval.

In addition, localities with projects passing through have established steering committees on compensation, support and resettlement to ensure the progress of site clearance for the project.

Chairman of Dak Lak province, Mr. Pham Ngoc Nghi surveyed the construction site of Khanh Hoa – Buon Ma Thuot expressway.

Before that, the Management Board of the construction investment project of traffic and agriculture and rural development in Dak Lak province had prepared a detailed plan for the implementation of component 3 of the highway construction investment project. Khanh Hoa – Buon Ma Thuot phase 1.

Specifically, the timelines for completing key tasks are as follows: Approve component 3 project before January 20, 2023, develop a plan to complete and approve the project on November 29, 2022; develop a plan to complete the environmental impact assessment on October 27, 2022 and approve it on November 21, 2022; Deployment of site clearance landmarks (land clearance) from September 25, 2022 and completed landmark planting on December 24, 2022. The handover work is carried out in parallel with the landmark planting, starting from November 9, 2022, to January 3, 2023, completing the handover of the project site clearance landmark…

The Khanh Hoa – Buon Ma Thuot expressway project will be started in 2023.

According to the pre-feasibility study report of the Khanh Hoa – Buon Ma Thuot expressway project, which has been submitted to the Prime Minister by the Ministry of Transport for appraisal and submitted to the National Assembly for consideration and decision on investment policy, the project has a good starting point. at the intersection between National Highway 26B and National Highway 1, Nam Van Phong port area, Ninh Hoa town (Khanh Hoa); the end point intersects with Ho Chi Minh road avoiding the east of Buon Ma Thuot city (Dak Lak).

According to the plan, the Khanh Hoa – Buon Ma Thuot expressway has a scale of 4 lanes, about 117.5 km in length; in which, the section through Khanh Hoa about 32.7 km, through Dak Lak province about 84.8 km.

The whole route is expected to build 49 bridges on the main line, 7 overpasses and 3 tunnels, including: Phuong Hoang tunnel about 2,100 m long, Ea Trang tunnel about 700 m long and Chu Te tunnel about 700 m long. The project is proposed to use the state budget, the total investment is about 21,935 billion VND; Construction is expected to start in 2023 and be completed and put into operation in 2026.


The article is in Vietnamese

Tags: Dak Lak develops detailed plan Khanh Hoa Expressway Project

PREV Thai Binh commends 47 typical tax paying businesses and individuals in 2021
NEXT Propagating and mobilizing people to raise awareness of safety protection of power grid corridors