Realizing the Dong Dang – Tra Linh – Final Expressway Project

--

Last period: Putting effort into site clearance for the Dong Dang – Tra Linh expressway project

Determining site clearance work The Dong Dang – Tra Linh expressway construction investment project is the province’s key political task in 2024, so from the beginning of the year, with the highest determination , the entire political system from the province to the grassroots, especially localities with expressways passing through, concentrate wholeheartedly, wholeheartedly, and with all their strength; innovate, be flexible and do propaganda work one step ahead, clear land early, create clean ground to serve the project.

Key political tasks of the province

Dong Dang – Tra Linh expressway project phase 1 has a length of 93.35 km, total investment of 14,167 billion VND. The starting point is at the intersection of Tan Thanh border gate, Van Lang district (Lang Son) and the ending point is at the intersection with National Highway 3 in Chi Thao commune (Quang Hoa). Embarking on project implementation, in addition to related legal procedures, the province is focusing its efforts on site clearance. Secretary of the Provincial Party Committee Tran Hong Minh said: Land clearance is a difficult and complex job, including many tasks with many difficulties and obstacles that need to be resolved, requiring the entire political system from the province to the grassroots to be highly determined. , make great efforts, act decisively, put all your heart, all your heart, all your strength, no side talk, no back talk. During the implementation process, attention should be paid to land recovery, compensation, and resettlement support because this is a sensitive issue directly related to the rights and obligations of the people. Land clearance work must be carried out drastically with the highest political determination…

In order for site clearance work to achieve results, on January 27, 2024, the Provincial People’s Committee launched the “100 day and night peak campaign to complete site clearance project of Dong Dang – Tra Linh expressway construction investment project”. Chairman of the Provincial People’s Committee Hoang Xuan Anh affirmed: The project plays a very important role in the socio-economic development of the country in general, and of Cao Bang and Lang Son in particular. “The peak campaign of 100 days and nights to complete the project clearance work” demonstrates the will, belief, aspiration, and very high determination of the Party Committee, government and people of the province in implementing the project. At the same time, strongly arousing patriotism, the spirit of emulation, the will to fight, and the victory of the Dong Khe Victory and the 1950 Border Campaign. Therefore, the Chairman of the Provincial People’s Committee called on all officials, Party members, civil servants, public employees, workers, officers, soldiers of the armed forces and people of all walks of life in the province, especially districts, cities, relevant agencies and units to the site clearance work in the project area, upholding the spirit of solidarity, unity, promoting intelligence, joining forces, unanimity, contributing efforts and determination to complete the site clearance task, contributing to speeding up the project progress. The project aims to maximize opportunities and advantages to promote rapid and sustainable socio-economic development of the province.

The province’s delegation directly went to the field to grasp the site clearance work in Thach An district.

Immediately after the launching ceremony, the province worked with Lang Son province to direct the Center for Land Fund Development and Site Clearance in Van Lang and Trang Dinh districts to organize an inventory of land, assets and crops within the scope of project implementation. The leaders of the two provinces continuously have field trips to grasp the site clearance work, the thoughts and aspirations of the people in the project area and directly give instructions to remove difficulties and obstacles related to the project. arrange resettlement for people. Require the units after construction to return the site of the system of infrastructure works, irrigation canals, water mines, residential roads, electricity lines…

Departments, branches, branches, 2 districts of Thach An, Quang Hoa and construction contractors are well involved in mobilizing and propagandizing people to relocate their houses, land, and crops early; Closely coordinate to remove obstacles in site clearance and promptly hand over the site to the construction contractor; Focus on completing the counting work; Accelerate the construction progress of resettlement areas. Review each specific task according to functions and tasks and propose solutions to effectively implement the work of extracting and measuring land clearance maps; compensation, resettlement support, training support, career change and job search, support for stabilizing life and production. Strengthen inspection and supervision. The construction unit prepares human and material resources ready for construction when the locality hands over the site…

After being propagated and mobilized, people in the project area clearly understood the Party’s guidelines, policies and laws of the State on compensation and site clearance, and basically agreed and agreed. Many households maximize the revolutionary homeland tradition, the spirit of self-reliance, self-reliance, solidarity, consensus, and emulation to quickly hand over the site to a joint venture of investors to carry out project construction to ensure progress. degree, before receiving compensation. Mr. Hoang Van Trong, Na Tuc hamlet, Duc Xuan commune (Thach An) has a house, agricultural land and more than 1 hectare of forest that must be completely relocated to a new place, said: Through propaganda and advocacy, I clearly understand the benefits the expressway brings in local socio-economic development, so I am ready to relocate all houses, fields and gardens to new places; Encourage family, relatives, and party members in the neighborhood to voluntarily sign a commitment before being paid compensation and hand over the site to investors soon.

Localities are flexible in site clearance

In Thach An district, the project passes through 16 hamlets in 5 communes and towns with a route length of about 21.63 km. There are 713 households in the land clearance area, 87 households in the resettlement area. Chairman of Thach An District People’s Committee Nong The Phuc said: With a large amount of work, in the spirit of removing all difficulties and removing each bottleneck, the district has increased extensive propaganda and organized direct dialogue with the people about the issue. Compensation and site clearance support policy in the direction of openness and transparency, ensuring maximum legal rights of people whose land and assets are recovered. Establish 2 land clearance teams to carry out counting; Coordinate with the Provincial Traffic Works Investment Project Management Board to receive documents and marker posts to serve compensation and site clearance work. Promulgate plans for land recovery, investigation, survey, measurement and counting in communes and towns. Up to now, the Party Committee and local authorities have basically coordinated to complete the steps in the recovery and site clearance process. Conducted counting and measuring more than 102 hectares of land, assets, and crops in 16/16 hamlets; There are 107 houses that need to be relocated, of which 75 households wish to arrange centralized resettlement. The Land Clearance Council and the district compensation counting team come up with plans and estimates for 659 affected households in Dong Khe town, Duc Xuan, Le Lai, Van Trinh, and Thuy Hung communes. By April 10, 2024, the entire district had moved 178 graves out of the scope of project implementation; 12/16 hamlets handed over more than 17 km (approximately 79 hectares) of land to construction enterprises.

In Quang Hoa district, District Party Committee Secretary Do Van Thang said: Determining land clearance and resettlement work is an important political task of the locality, so during the implementation process, we direct the units , localities must be cautious because this is a sensitive issue directly related to the rights and obligations of the people. Timely resolve arising problems, problems and difficulties; Regularly follow up direct dialogue with people on compensation policies and land clearance support in a public and transparent manner, ensuring maximum legal rights of people whose land and assets are recovered. Strengthen propaganda to households and communes in the project area so that people understand the meaning and great value that the project brings. Promoting the role of secretary, village head and front committee head, reputable people in the community as the core in propagating contributions and helping the district hand over the site early to the investor and construction unit to promote speed up project construction progress. In the spirit of removing all difficulties and bottlenecks, up to now, the district has handed over more than 11 km to the construction unit (equivalent to more than 70 hectares).

In Lang Son province, the Center for Land Fund Development and Site Clearance in Van Lang and Trang Dinh districts is organizing an inventory of land, assets and crops within the scope of project implementation. By April 7, 2024, Van Lang district counted 29.16 hectares/166.66 hectares (reaching 17.49% of the total recovered area) of 220/891 households and 329 graves that had to be relocated; Advance payment of 3.1 billion VND for relocation to 103 households, 42 households moved graves. Trang Dinh district counted 91 households with an area of ​​more than 13 hectares (reaching 5.8 km); Moved 66/197 graves.

The investor consortium focuses on mobilizing human resources, equipment and machinery to level the ground at km 53 in Tuc Nga hamlet, Duc Xuan commune (Thach An).

When the site is handed over, to ensure progress as committed, these days, at some key locations in Tuc Nga, Na Tuc, Na Pa, Pac Khoang, Duc Xuan commune, Ban Cam, Doc Lap, Na Danh, Na Ngai, Tan Viet, Le Lai commune, Ban Neng hamlet, Thuy Hung commune, Na Luong hamlet, Residential group 1, Na De hamlet, Dong Khe town, joint venture investors are focusing on mobilizing mobilize human resources, machinery and equipment, take advantage of dry weather to level the ground, and handle complex terrain to ensure the overall progress of the project.

With the spirit of determination and determination, efforts to remove difficulties and obstacles of the entire political system and the joint efforts and unanimity of the people of the project area, according to the province’s plan, site clearance work is guaranteed to be correct. , ahead of schedule, by June 15, 2024, 100% of the premises will be handed over to investors to implement the project. The next steps of the project will continue to be implemented by the province in accordance with the direction of Prime Minister Pham Minh Chinh: Construction of the Dong Dang – Tra Linh expressway in the spirit of the Dong Khe Victory, striving for the end. In 2025 and early 2026, the entire route will open to traffic.

TERM 1: REMOVING THE “BOTTLE” IN TRANSPORTATION INFRASTRUCTURE

TERM 2: RESOLVING DIFFICULTIES IN CAPITAL MECHANISM FOR PROJECTS

Thai Ha


The article is in Vietnamese

Tags: Realizing Dong Dang Tra Linh Final Expressway Project

-