The case of false acceptance of the irrigation project in Dak Lak: How does the investor report?

--

On April 24, the Department of Agriculture and Rural Development of Dak Lak province reported to the People’s Committee of this province to review and provide information and documents related to the canal solidification project and works on the canal. Buon Triet irrigation, Lak district.

According to Dak Lak Department of Agriculture and Rural Development, with the request of the Provincial People’s Committee to provide relevant documents, Dak Lak Irrigation Works Management Company Limited (Dak Lak Irrigation Company, project investor) has reported that there was a search but not many relevant records and documents were found in the archives.

A canal at the Buon Triet irrigation canal project, although not constructed of concrete, was still accepted (Photo: Uy Nguyen).

Specifically, the company has checked, reviewed, and searched for currently stored records and documents, but there are no records, documents, or documents related to the project inspection of the People’s Committee of Dak Lak province and relevant departments, divisions and branches.

According to Dak Lak Irrigation Company, in 2011 people hindered the project’s construction due to disagreement on compensation and support levels, so construction had to be temporarily stopped. The company reported to the Provincial People’s Committee for advice. religion. However, up to now the company has not found any written instructions or resolutions from the Provincial People’s Committee currently stored at the company.

In addition, the company also reported on investment monitoring and evaluation of the project implementation process to the Dak Lak Department of Planning and Investment.

Through review, the investor did not find many records and documents related to the Buon Triet irrigation canal project (Photo: Uy Nguyen).

In addition, in 2017, Dak Lak Irrigation Company submitted a request for capital allocation to repay debt for the above project. In particular, the Company has requested the competent authority to settle the completed volume that has been accepted. However, up to now the company has not received instructions or solutions from the Provincial People’s Committee or Dak Lak Department of Finance.

Through checking current archived records, Dak Lak Department of Agriculture and Rural Development did not find any documents from the investor and the Provincial People’s Committee related to the construction process of phase 2 of the project, so this Department did not know the specifics to report.

“The investor, Dak Lak Irrigation Company, is responsible for storing records. Through the direction of the province, the Department has sent two documents to this company to provide documents. Due to the incident “It happened quite a long time ago. Some documents found by the company have been compiled to send to the province. There are still many documents that have not been found and the company is continuing to review,” informed the leader of the Department of Agriculture and Rural Development.

Like Dan Tri Reportedly, the Dak Lak Provincial Police Investigation Agency has decided to prosecute a criminal case for violating regulations on construction investment causing serious consequences at the canal solidification project. and works on Buon Triet irrigation canal (Lak district).

The Police Investigation Agency determined that there were individuals and units involved in falsely increasing the construction volume for acceptance and payment of more than 7.4 billion VND at this project.

In March 2007, the People’s Committee of Dak Lak province approved adjusting the scale of the project to solidify the canal and works on the Buon Triet irrigation canal, with a total investment of nearly 89 billion VND from Government Bond capital. The project is invested by Dak Lak Irrigation Company.

During the implementation process, phase 1 has constructed the main canal, N1, N2, N2-2, N2-3, with a total investment of over 57 billion VND. The investor has organized the construction, completed the acceptance test, and handed it over for use.

For phase 2 being investigated by the police, including: branch canals N2-5, N2-6, N2-7, N2-8, N2-10, N2-11, N2-13, flood drainage canal, management building and accompanying equipment with a total investment of over 31 billion VND.

The phase 2 project had to be paused since 2011 because of land problems due to people not agreeing with the level of support.

The article is in Vietnamese

Tags: case false acceptance irrigation project Dak Lak investor report

-