More than 3 years have not completed 9.5 km of road in Van Don

--

People are suffering, investors are sad because the provincial roads are degraded

Provincial Road 334 is considered the “backbone” connecting functional subdivisions of Van Don Economic Zone, passing through the communes of Doan Ket, Ha Long, and Van Yen.

Provincial Road 334 is seriously degraded

Faced with such an important role, in May 2021, Quang Ninh province invested in upgrading and expanding provincial road 334, with a total capital of nearly 1,500 billion VND; In which the cost of site clearance is more than 650 billion VND. The project was assigned by the People’s Committee of Quang Ninh province to the Quang Ninh Provincial Traffic Construction Investment Management Board as the investor.

The project has a total length of 9.5 km, the starting point connects to the main road of Cai Rong Urban Area and the ending point connects to the intersection of Van Don Airport – Complex Park.

It is worth mentioning that, contrary to expectations about the dream coastal road, bringing happiness to people and convenience for investors coming here, over the past 3 years, tourists, local people, Investors have to suffer when traveling on roads full of “potholes” and “elephant holes”.

For many years, people on both sides of Provincial Road 334 have lived miserable lives because of the “road of suffering”.

The most miserable thing is that on sunny days, the dust and dirt cause environmental unsanitary conditions. On rainy days, it is muddy and the road surface is full of stagnant ponds.

Mr. Nguyen Trung Hoa (48 years old, residing in H.Van Don) said: “Every time I go on Provincial Road 334 passing through Ha Long commune, I feel scared. The road is bumpy and difficult to travel on. If you are not steady at the wheel, you can “If the project was started 3 years ago, people would soon have a new route, but progress is still sluggish.”

Provincial Road 334 is considered the “backbone” of Van Don Economic Zone, so the current serious deterioration of this road greatly affects the investment environment. Many businesses with projects around the route are bored when talking about this “painful road”.

An investor from Hanoi lamented: “The trillion-dollar resort complex was started a few years ago and has now been completed by the investor; meanwhile, route 334 will become more and more degraded if it lasts as long as it does. This will greatly affect the quality, promotion and attraction of investment into Van Don Economic Zone.”

Trillion road road is behind schedule because of land clearance capital increase

According to the Management Board of Investment and Construction of Transport Works in Quang Ninh province, the project to expand Provincial Road 334 is behind schedule. According to the initial plan, the 9.5 km long section mentioned above will be put into operation in June 2023; But up to now, the project has only completed 60% of the volume.

The project to upgrade and expand Provincial Road 334 has been unfinished for the past 3 years because there is no premises.

The project to upgrade and expand Provincial Road 334 has been unfinished for the past 3 years because there is no premises.

A representative of the Investment and Construction Management Board of traffic works in Quang Ninh province said that the reason for the slow progress was due to the project’s overcapitalization, stemming from site clearance work.

Specifically, to implement the project, Van Don District must reclaim more than 40 hectares, including: road land, land of more than 400 households and organizations located within the boundary line. However, up to now more than 3 years of implementation, contractors have only organized construction on about 40% of the area handed over by the locality. In particular, the first 2.9 km of the route is still intact and the last 2.5 km of the route has not been completed.

Recorded by PV Youth During the days of April 22 – 23, it was shown that along the project, only a few dozen workers were completing a number of small items, while the remaining construction vehicles were lying “covered”.

Mr. Nguyen Van Trung, Site Commander – 484 Joint Stock Company, said that the project’s delay in handing over the site had a great impact on contractors related to management costs, labor, and material price inflation. private…

“The consortium of contractors has arranged enough vehicles, machinery and equipment at the construction site but cannot organize construction implementation. The project is behind schedule for more than 1 year, causing the price increase for items to be more than 35% %. We hope that the authorities will soon solve the difficulties so that the road can be handed over on time,” Mr. Trung said.

The area of ​​Ha Long commune is constricted because there is no ground for further construction

The area of ​​Ha Long commune is constricted because there is no ground for further construction

According to the People’s Committee of Van Don District, regarding the site clearance of the above project, recently, the Inspection Committee of the Quang Ninh Provincial Party Committee has just proposed disciplining 17 local officials involved due to laxity and lack of inspection and supervision. resulting in the project being overcapitalized.

Currently, individuals who committed violations related to project site clearance compensation have basically overcome the consequences; At the same time, speed up the progress of handing over the premises to investors.

Exchange with Youth, a leader of H.Van Don said that after the project’s capital increased to more than 1,500 billion VND, the authority belonged to the ministries and branches of the Central Government; The locality is coordinating with funding authorities so that the project can continue to be implemented.

More than 3 years of work failed to complete 9.5 km of road in Van Don - Photo 5.

The project under construction does not have a site and lacks capital

For many years, people and tourists coming to Van Don have had to travel on crushed roads

For many years, people and tourists coming to Van Don have had to travel on crushed roads

Slow construction projects waste resources and state budget

Slow construction projects waste resources and state budget

More than 3 years of work failed to complete 9.5 km of road in Van Don - Photo 8.

Unfinished construction of a trillion-dollar project makes people suffer

More than 3 years of work failed to complete 9.5 km of road in Van Don - Photo 9.

Vehicles and equipment are gathered at the construction site waiting for construction site