The 50.7 billion VND monitoring project shows signs of causing loss and waste of 43 billion VND

--

The Cai Cung estuary area – where one of the three monitoring stations is located, has just been pointed out by the Inspectorate of Bac Lieu province as having many violations – Photo: CHI QUOC

On April 25, sources of Tuoi Tre Online said that the Inspectorate of Bac Lieu province has just concluded an unexpected inspection of the project to build three automatic surface water monitoring stations in Bac Lieu province invested by the Department of Natural Resources and Environment of Bac Lieu province.

These three monitoring stations located in Nha Mat (Bac Lieu City), Cai Cung and Ganh Hao (both in Dong Hai district) have a total investment of more than 50.7 billion VND, implemented in the period 2017-2018.

The consulting and supervision unit… does not have a certificate of competency

Inspectors of Bac Lieu province concluded that the Department of Natural Resources and Environment appointed a contractor who did not have enough capacity to perform the project.

Specifically, the design consulting unit, the Branch of Public Transport Joint Stock Company, does not have an organizational capacity certificate to participate in construction survey and construction design activities; The supervision consulting unit, Ecological Solutions Company, does not have an organizational supervision capacity certificate to perform supervision consultancy.

The Department of Natural Resources and Environment established a project management team, but the participating members did not have professional expertise suitable for the work undertaken and paid concurrent allowances of more than 154 million VND.

For arising bidding packages, the Department of Natural Resources and Environment approves the contractor appointment plan before receiving written approval from the competent authority, and approves the construction contractor appointment results before approving the development estimate. born.

Through checking and comparing the imported goods declaration with the contract between the Department of Natural Resources and Environment and the International Progress Joint Stock Company (AIC Company) for 25/70 pieces of equipment, the difference in amount is more than 5.7 billion VND.

AIC Company also provided and installed a number of equipment that did not comply with the financial proposal and contract documents; unknown label and origin; Different serial number, different model, different manufacturer with a total amount of more than 2.2 billion VND.

According to the report of the Department of Natural Resources and Environment to the inspection team, there were three damaged devices worth more than 2.9 billion VND, 19 unused devices with a total amount of more than 8.1 billion VND, there were signs of wasting state budget.

Also according to the Inspectorate of Bac Lieu province, this project has been accepted and completed since May 2020. Up to now, many devices have been damaged, cannot be put into operation, the devices have expired warranty period and solutions. To repair, the feasibility of the project is not achieved compared to the original goals of the project, and does not bring socio-economic efficiency.

Transferred to investigation agency because of signs of crime

A coastal area of ​​Bac Lieu province – Photo: CHI QUOC

The Inspectorate of Bac Lieu province proposed that the Chairman of the People’s Committee of Bac Lieu province direct a formal review of the director of the Department of Natural Resources and Environment and relevant individuals (at the time in charge) in leadership, Direct the organization and implementation of the three monitoring station project to avoid the above-mentioned shortcomings, limitations and violations.

Review and clarify the responsibilities of the leadership of the Department of Natural Resources and Environment at the present time (focus on the director) in leadership and direction when the project is completed and put into use; There is no timely solution to handle the problems that arise with some equipment that has been accepted. During the trial run, they were damaged so they have not been put into operation for more than three years.

Formal criticism of the director of the Department of Planning and Investment and relevant individuals at the time in charge of the appraisal and approval of the feasibility study report was not in accordance with the planning and did not bring results. invest effects.

The Bac Lieu Provincial Inspectorate also transferred the case file showing signs of crime to the Bac Lieu Provincial Police Investigation Agency for: Department of Natural Resources and Environment (with assigned duties as investor, role is the director at the time in charge); project management consulting unit, feasibility study report preparation consulting unit, equipment price appraisal consulting unit, construction unit is AIC Company, supervision consulting unit and other agencies , relevant units, organizations, and individuals during the project implementation process have limitations, shortcomings, violations, and signs of loss or waste of the entire project’s state budget. is over 43 billion VND.

The article is in Vietnamese