Proposal to build a bridge across the Ninh Co River in Nam Dinh with a lifespan of 100 years

Proposal to build a bridge across the Ninh Co River in Nam Dinh with a lifespan of 100 years
Proposal to build a bridge across the Ninh Co River in Nam Dinh with a lifespan of 100 years
--

The investment project to build Ninh Cuong bridge across Ninh Co river on National Highway 37B is a level I bridge project, with a useful life of 100 years. The project construction location is in two districts: Truc Ninh and Nghia Hung, Nam Dinh province.

The investment project to build Ninh Cuong bridge across Ninh Co river on National Highway 37B is a level I bridge project, with a useful life of 100 years. Project construction location in Truc Ninh and Nghia Hung districts, Nam Dinh province (In photo: Current Ninh Cuong Pontoon Bridge)

Thang Long Project Management Board has just submitted a report (second time) requesting the Ministry of Transport to approve the feasibility study report of the investment project to build Ninh Cuong bridge across Ninh Co river on National Highway 37B.

According to Thang Long Project Management Board, the Ninh Cuong bridge construction project across Ninh Co river on National Highway 37B has been approved by the Prime Minister for investment policy in Decision No. 22/QD-TTg dated January 7, 2022, the project is approved by the Prime Minister. Investing with loan capital from the Korean Government and counterpart capital from the Vietnamese Government through the VNM-48 Loan Agreement.

At the same time, the Ministry of Transport issued Decision No. 413/QD-BGTVT dated April 9, 2024 on approving the investment policy adjustment of the project “Construction of Ninh Cuong bridge across Ninh Co river on National Highway 37B” using loan capital. ODA of Korea.

According to the Report of Thang Long Project Management Board, the investment project to build Ninh Cuong bridge across Ninh Co river on National Highway 37B is a level I bridge project, with a useful life of 100 years. The project construction location is in two districts: Truc Ninh and Nghia Hung, Nam Dinh province.

Regarding scale and technical standards, the Ninh Cuong bridge construction project has a total length of about 1.65 km, including: Ninh Cuong bridge length is about 670 m and the path is about 980 m.

The bridge over the Ninh Co River is designed permanently with reinforced concrete and prestressed reinforced concrete, bridge width is 12m, including 2 motor vehicle lanes, 2 rudimentary vehicle lanes, and railings; The approach road to the bridge is built according to class III plain road standards, the road bed is 12 m wide, and the design speed is 80 km/h.

The project is proposed to be built with a total investment of about 581.18 billion VND. The capital structure includes: Loan capital of 465.72 billion VND (about 19.337 million USD), domestic counterpart capital of about 115.467 billion VND. Project implementation period is from 2023 – 2027./.

According to tapchigiathong.vn


The article is in Vietnamese

Vietnam

Tags: Proposal build bridge Ninh River Nam Dinh lifespan years

-