The goal of this transformer station project is to increase the ability to supply electricity to Thanh Hoa province and the North Central region.

The National Power Transmission Corporation has just been approved by the People’s Committee of Thanh Hoa province as the investor to implement the 500kV Thanh Hoa transformer station project.

The project’s goal is to increase the ability to supply electricity to Thanh Hoa province and the North Central region; Transmitting power generated from Quynh Lap Power Center, Quang Trach Power Center and Nam Dinh Power Center into the national power system through 220kV and 500kV synchronous power grids…

The project has a total investment capital of more than 1,444 billion VND; Of which, equity accounts for 30% of total project investment; Commercial loans account for 70% of the total project investment. The total land use need of the project is about 14.31 hectares in Thieu Tien, Thieu Phuc, Thieu Vien, Thieu Ly, Thieu Trung communes and Hau Hien town, Thieu Hoa district.

>> The 500kV circuit 3 line project is still ‘waiting’ for premises and equipment

New construction scale of 500kV transformer station; Construction of a new 4-circuit line to connect the 500kV Thanh Hoa Transformer Station to the space of pillars T03-T05 of the existing 220kV Nong Cong – 220kV Thanh Hoa Line (220kV Ba Che).

The progress of completing and putting the project into operation is within 6 months from the time the State handed over the land.

Illustration photo

Previously, at the end of 2023, the People’s Committee of Thanh Hoa province also decided to approve the investment policy at the same time as approving the investor for the National Power Transmission Corporation to implement the 220kV Transformer Station project in the Economic Zone. Nghi Son airport and connection lines.

The project’s expected land area is about 14.94 hectares; Of which, the station construction area is about 8.28 hectares; The road area to the station is about 4.99 hectares; The area of ​​column foundation locations is about 1.67 hectares; The land area affecting the connection line corridor is about 7.24 hectares (the corridor area does not require land acquisition; the land use purpose is not changed).

Design capacity is 750MVA (including 3 transformers 220/110/22kV – 250MVA). The project has a total investment capital of more than 675.03 billion VND, of which, equity capital is 202.5 billion VND (accounting for 30%); Bank loan capital is 472.5 billion VND (accounting for 70%).

The National Power Transmission Corporation is also the investor implementing the 500kV Thanh Hoa – Nho Quan Branch – Ha Tinh line project. The scale of the project is to build a new 500kV Thanh Hoa line – Nho Quan – Ha Tinh branch, 2 circuits about 5km long, from the Thanh Hoa 500kV gate column to the connection location between pillars T301 – 302 on the 500kV line. Nghi Son – Nho Quan (circuit 2) exists. The project has a total investment of more than 256.3 billion VND.

>> Revealed that the group won 10 bidding packages of the 500kV circuit 3 line project (extended)


The article is in Vietnamese

Vietnam

Tags: Welcoming investment wave Thanh Hoa additional #500kV transformer station project billion VND

-

PREV Kon Tum College closed the 4th Teachers’ Lecture Conference in 2024
NEXT Bustling Cua Lo fishing wharf at dawn