Crystal Holidays Harbor Van Don is located in Ao Tien Luxury Port and Tourism Urban Area, Ha Long commune, Van Don district, Quang Ninh province. From the project, you can easily move to Ao Tien high-class port in just 2 minutes, 5 minutes to Van Don International Airport, 10 minutes to Van Don District Medical Center, 15 minutes to Cai Rong port. …

Project scale of Crystal Holidays Harbor Van Don Quang Ninh Resort

Perspective of Crystal Holidays Harbor Van Don Resort.

Crystal Holidays Harbor Van Don Resort is developed on a land area of ​​more than 2.6 hectares with a construction density of 58.2%.

The project scale includes 5 towers labeled A – The Victory, B – The Oasis, C – The Harmony, D – Liberty and E – Heritage with 28-34 floors high. Building E is a 5-star hotel building, the remaining 4 buildings are apartments.

The project provides the market with 367 hotel rooms and 1,907 resort apartments with a total investment of 3,611.5 billion VND. In addition, the project also has an International Conference Center with 1,500 seats.

Floor plan of Crystal Holidays Harbor Van Don Resort.

The project integrates 102 natural and man-made amenities such as Asian-European style restaurant, night bar, gambling club, sky bar, cigar lounge, infinity pool, four-season swimming pool, treatment spa. High class, 11D cinema….

Crystal Holidays Harbor Van Don: Resort project in Quang Ninh

Amenities perspective of Crystal Holidays Harbor Van Don Resort.

In addition, Crystal Holidays Harbor Van Don also offers unique and new experiences for visitors, such as viewing the bay by helicopter, traveling on 5-star yachts, playing golf at sea, and diving to see coral reefs. Snorkeling at the bottom of the sea, trekking in the primeval forests on the island and many other interesting games…

Project information for Crystal Holidays Harbor Van Don Quang Ninh Resort

Crystal Holidays Harbor Van Don is a resort project invested by Everland Van Don Joint Stock Company, Mai Quyen Tourism Company Limited is the developer and constructed by Delta Group.

Everland Van Don Joint Stock Company was established on April 22, 2019, with an initial charter capital of 350 billion VND. Mr. Le Dinh Vinh – Chairman of the Board of Directors of Everland Group (EVG) is the representative of EVG’s capital contribution of 210 billion VND (equivalent to 60% ownership) in Everland Van Don. At Everland Van Don, Mr. Vinh holds the position of Vice Chairman of the Board of Directors and General Director.

In April 2021, the Board of Directors of Everland Group approved the policy of increasing charter capital at Everland Van Don. Accordingly, Everland Van Don issued 40 million shares, par value of 10,000 VND/share, of which Everland Group has the right to buy 24 million shares with a total value of 240 billion VND to maintain 60% ownership in Everland Van Don. .

Crystal Holidays Harbor Van Don is located at Lot M1, Ao Tien luxury port and tourist urban area, and has been approved by the People’s Committee of Quang Ninh province to adjust the detailed construction planning at a scale of 1/500 in Decision No. 68. /QD-UBND January 8, 2019.

On April 23, 2019, Everland Van Don Joint Stock Company and Mai Quyen Tourism Company Limited held a groundbreaking ceremony for the Crystal Holidays Harbor Van Don project,

On April 30, 2022, the project officially started construction, expected to be completed and put into operation in 2024.

According to the investor’s progress update in March 2024, the project has completed 100% of the tunnel construction of 5 interconnected buildings. Currently completing acceptance of the foundation tunnels of 3 blocks of buildings C, D and E to construct the body.

Crystal Holidays Harbor Van Don project progress in March 2024.

The podium of building A (Victory) and building B – The Oasis have been built to the 7th floor by March 2024. Van Don Crystal Island beach has been basically completed. The base blocks of buildings C and D have been installed with cranes to prepare for the base block construction.

Quick information Crystal Holidays Harbor Van Don Resort Quang Ninh

Project: Crystal Holidays Harbor Van Don

Total area: 2.6 hectares

Location: Lot M1, Ao Tien luxury port and tourist urban area, Ha Long commune, Van Don district, Quang Ninh province

Total investment: 3,611.5 billion VND

Type: hotel apartments

Year of commencement: April 30, 2022

Investor: Everland Van Don Joint Stock Company

Year completed:


The article is in Vietnamese

Tags: Crystal Holidays Harbor Van Don Resort project Quang Ninh

-

NEXT One more person was swept away by floodwaters and went missing on the Po Co River