On May 13, the road connecting Ben Rung bridge was opened to traffic

--

To ensure synchronous connection with the Ben Rung bridge project, which is expected to be put into operation in the middle of May, on April 25, comrade Cao Tuong Huy, Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People’s Committee went to Inspect the organization and construction of the road connecting Ben Rung bridge.

Chairman of the Provincial People’s Committee Cao Tuong Huy requested that on May 13, technical traffic will be opened to synchronously connect the route connecting to Ben Rung bridge.

The road project connecting Ben Rung bridge started in May 2023 with a scale of 2.2km, the starting point connects to Ben Rung bridge, the last point connects to the intersection of provincial road 338, the section passing Song Khoai commune (Quang Yen town). ). The road is designed according to level III plain standards with 6 lanes, including 4 motor vehicle lanes and 2 mixed vehicle lanes, along with a system of median strips, sidewalks, green landscape, lighting and lowering patterns. floors to ensure traffic safety.

Reporting to the Chairman of the Provincial People’s Committee at the inspection, the investor representative said that up to now the total volume of items has reached over 70%, the contractors have completed the construction of the sewer system and foundation. Fast routes at the intersection with provincial road 338 and connecting road. At the same time, unloading has been carried out at weak soil treatment locations…, progress is currently following the plan.

Currently, contractors are focusing on speeding up construction, determined to ensure progress according to plan.

After listening to the progress report and directly inspecting the organization of construction of the road connecting Ben Rung bridge, the Chairman of the Provincial People’s Committee highly appreciated the efforts and determination of the investor and contractors. In particular, the team of workers went out and organized construction even during Tet holiday, without interrupting the construction site.

Emphasizing the role and progress of the project in the province’s development plan to form a seamless and complete transportation system with Hai Phong, the Chairman of the Provincial People’s Committee suggested that it is currently in the construction phase. During the sprint, contractors need to continue mobilizing human resources, vehicles, overtime, and crews to carry out simultaneous construction with the highest goal of ensuring the set progress.

However, contractors need to ensure quality, technique, aesthetics and especially construction site safety and not be subjective or negligent. Investors need to strengthen inspection, supervision and speed up progress.

The goal is that by April 5, the intersection will be completed and the road surface will be paved with crushed stone and by May 13, the entire route will be technically opened to traffic, ensuring vehicles can move back and forth between the connecting roads. and Ben Rung bridge.


The article is in Vietnamese

Vietnam

Tags: road connecting Ben Rung bridge opened traffic

-

PREV Career counseling for 9th grade students in Mo Cay Nam district
NEXT Announcing the decision of the Chairman of Binh Thuan province on personnel work