Transferred the police to investigate the project of 3 monitoring stations related to AIC

Transferred the police to investigate the project of 3 monitoring stations related to AIC
Transferred the police to investigate the project of 3 monitoring stations related to AIC
--

April 26, according to reporter sources Dan tri, Bac Lieu Provincial Inspectorate has just concluded an unexpected inspection of the project to build 3 automatic surface water monitoring stations in Bac Lieu province. The inspection agency discovered a series of serious violations.

The project to build 3 automatic surface water monitoring stations has been implemented since 2017, with a total investment of more than 50 billion VND, invested by the Department of Natural Resources and Environment (NRE) of Bac Lieu province.

A monitoring station in Bac Lieu province (Photo: CTV).

The project has 2 main packages: construction of 3 monitoring stations won by Thanh Khiem Company Limited worth more than 1.8 billion VND; The equipment supply and installation package won by Progressive International Joint Stock Company (AIC Company) is worth more than 39 billion VND.

According to the inspection agency, some goods and equipment were purchased by AIC Company through intermediaries without a sales contract from the owner or manufacturer; There are 25/70 pieces of equipment whose contract price is more than 31 billion VND, but the actual imported value is only 25.5 billion VND, a difference of more than 5.7 billion VND.

Through inspection of the current status, it was found that AIC Company provided and installed a number of equipment that was inconsistent with the contract such as goods with unknown labels and origin; different machine serial number,…

The inspection agency also clearly pointed out the work of submitting and approving investment policies; prepare a feasibility study report; Investment implementation, capital payment and settlement, etc. have had many shortcomings and violations.

The project has been accepted and completed since May 2020 until now (more than 3 years), many equipment has been damaged, cannot be put into operation, the feasibility has not been achieved compared to the initial goal set, no brings economic and social efficiency,…

The illegal content in the project shows signs of violating State regulations and shows signs of causing loss and waste of the budget of over 43 billion VND.

The inspection agency recommends reviewing and handling the responsibilities of the Director of the Department of Natural Resources and Environment, the Director of the Department of Planning and Investment and relevant individuals at the time in charge.

Bac Lieu Provincial Inspectorate also transferred files showing signs of crime to the investigation agency to clarify the Department of Natural Resources and Environment (main role is Director at the time in charge), supervision consulting unit, reporting consulting unit. Feasibility study reports, equipment price appraisal consultants, AIC Company construction unit, supervisors and relevant organizations and individuals when implementing projects with signs of budget loss.

The article is in Vietnamese

Vietnam

Tags: Transferred police investigate project monitoring stations related AIC

-