Dong Nai issued an ‘ultimatum’ on site clearance for 3 key projects

Dong Nai issued an ‘ultimatum’ on site clearance for 3 key projects
Dong Nai issued an ‘ultimatum’ on site clearance for 3 key projects
--

On April 26, Dong Nai Provincial People’s Committee held a conference to sign a contract “30 days and nights to carry out compensation and site clearance for key projects in the province”.

The units signed a 30-day agreement to carry out compensation and site clearance for key projects

According to Acting Chairman of the Provincial People’s Committee Vo Tan Duc, on February 13, through an actual inspection of the progress of implementation of key national projects in the province, the Prime Minister finalized the progress of handing over the entire Road project. Bien Hoa – Vung Tau Expressway before June 30, 2024.

However, according to assessments, the progress of capital disbursement and progress of key works and projects in the province is still slow. The main reason is that compensation and site clearance work faces many difficulties and obstacles.

A small number of areas of the Bien Hoa – Vung Tau Expressway were handed over to the construction unit

Previously on April 17, at the Conference to review the progress of implementing key works and projects in the province, Secretary of Dong Nai Provincial Party Committee Nguyen Hong Linh directed the launch of implementation. Commitment to 30 days and nights of compensation work, Bien Hoa – Vung Tau Expressway”> site clearance for 3 key projects including: Bien Hoa – Vung Tau Expressway Project, Cai River Coastal Road Project and Project Main road of Bien Hoa city.

Therefore, Acting Chairman of the Provincial People’s Committee Vo Tan Duc requested relevant units to work in a spirit of speed during the 30 days and nights, with maximum concentration of forces and means, and to arrange time to suit the actual situation. Currently, the site clearance work for the 3 projects mentioned above has achieved and exceeded the set goals according to the signed commitment.

According to the plan put forward by the People’s Committee of Dong Nai province, within 30 days and nights (April 26 to May 26), departments, branches, branches, People’s Committee of Bien Hoa City, People’s Committee of Long Thanh district and People’s Committees of communes, wards and towns where There are key projects that must complete compensation and site clearance work. In particular, the Bien Hoa – Vung Tau Expressway project, before June 30, must approve the compensation plan, land recovery and hand over the site to the investor to implement the project.

Dong Nai province’s leaders also assigned the Department of Home Affairs to implement regulations on supervision, rewards, and penalties for units and individuals in implementing the contract signing.

Manh Thang

The article is in Vietnamese

Vietnam

Tags: Dong Nai issued ultimatum site clearance key projects

-

PREV National Assembly delegates meet voters before the 7th session in Que Phong, Con Cuong
NEXT One more person was swept away by floodwaters and went missing on the Po Co River