(Thanhhoa.dcs.vn): According to a report from the Department of Natural Resources and Environment, in the first 4 months of 2024, the whole province has cleared 1,034.05 hectares of land, reaching 47.72% of the plan. plan, 1.52 times higher than the same period; Implementation progress is as follows:

There are 12 districts with site clearance rate reaching over 50% of the plan, including: Tho Xuan 59.62 hectares, equal to 98.77%; Quang Xuong 122.06 hectares, equal to 70.87%; Cam Thuy 36.75 hectares, equal to 66.68%; Thieu Hoa 99.77 hectares, equal to 65.76%; Yen Dinh 45.2 hectares, equal to 63.66%; Nga Son 33.69 hectares, equal to 55.79%; Quan Son 9.72 hectares, equal to 54.92%; Lang Chanh 35.55 hectares, equal to 54.07%; Hau Loc 30.44 hectares, equal to 51.82%; Nong Cong 47.29 hectares, equal to 51.72%; Nhu Xuan 48.06 hectares, equal to 51.4%; Nhu Thanh 41.19 hectares, equal to 50.99%.

There are 08 districts and towns with site clearance rates reaching from 40% to less than 50% of the plan, including: Thach Thanh 32.41 hectares, equal to 48.36%; Bim Son town 24.72 hectares, equal to 46.62%; Ngoc Lac 25.02 hectares, equal to 45.24%; Ha Trung 24.99 hectares, equal to 44.78%; Vinh Loc 27.25 hectares, equal to 44.14%; Trieu Son 44.24 hectares, equal to 43.11%; Ba Thuoc 3.44 hectares, equal to 42.89%; Thuong Xuan 14.49 hectares, equal to 42.18%.

There are 07 districts, towns and cities with clearance rates reaching less than 40% of the plan, including: Sam Son city 19.65 hectares, equal to 37.61%; Hoang Hoa 27.54 hectares, equal to 37.42%; Dong Son 34.66 hectares, equal to 34.39%; Nghi Son town 118.22 hectares, equal to 30.58%; Thanh Hoa city 22.58 hectares, equal to 26.32%; Muong Lat 4 hectares, equal to 12.72%; Quan Hoa 1.46 hectares, equal to 7.44%.

In general, site clearance for projects still faces difficulties and problems, such as: Determining the origin and time of land use is difficult, complicated, and takes a long time; Many projects are not eligible for site clearance; The land recovery process of some projects must go through many steps and take a lot of time, especially in places where land disputes occur; Funds allocated for site clearance work of some projects are not timely…

The article is in Vietnamese

Vietnam

Tags: Progress site clearance land projects province Electronic information portal Thanh Hoa Provincial Party Committee

-

PREV Quang Binh deploys investment in 500 social housing units in 2024
NEXT Dien Bien Phu – endless inspiration: Vietnam on the journey of Roman Karmen